Timeline

Slick Dashboard API Structure Link

API structure

Design Link

Design

Phase 1

To be developed components

ComponentDesignDevelopmentDocs & ExamplesTestingTotal (days)
Icon

(Readme)

1.51.50.50.54
Status:CompletedStart Date:22/10/2020End Date:27/10/2020Delay by days:
Grouped Icons

(Readme)

1.52.50.50.55
Status:CompletedStart Date:02/11/2020End Date:10/11/2020Delay by days:3.5

delay reason

Icon bar

(Readme)

1.52.50.50.55
Status:CompletedStart Date:11/11/2020End Date:18/11/2020Delay by days:
Chart

(Readme)

0.540.516
Status:CompletedStart Date:19/11/2020End Date:30/11/2020Delay by days:2

delay reason

Chart Action Card

(Readme)

1.51.50.50.54
Status:CompletedStart Date:01/12/2020End Date:07/12/2020Delay by days:1

delay reason

Prev Next Chart

(Readme)

1.53.50.50.56
Status:CompletedStart Date:08/12/2020End Date:21/12/2020Delay by days:4

delay reason

Expandable Chart Card(Business Component)

(Readme)

210.50.54
Status:CompletedStart Date:22/12/2020End Date:06/01/2021Delay by days:3

delay reason

Page Design (filter, data point, chart-action-card-list)3.54.50.50.59
Status:Start Date:End Date:Delay by days:

Skipped Components

  • action-card-tile
  • action-card-tile-list
  • bread-crumb
  • query-builder
  • data-points-action-card-list
  • graph-summary

Delay Reasons

Grouped Icon

  • Conversion of typescript components to javascript components and merging into existing code(2 days).
  • Homepage tickets and other tasks(1.5 days).Ticket Ids:
    • TW/GEN/2020/S07758
    • TW/ASRTU/2020/S07773
    • TW/GEN/2020/S07778
    • TW/BIHAREPROC/2020/S07722
    • TW/BIHAREPROC/2020/S07781
    • TW/DLGP/2020/S07792
    • TW/INDBANK/2020/S07768
    • Depts added on mails: NITIE,COTCORP

Chart

  • Payment History Screen issues(0.5 day).
  • Homepage tickets and other tasks(1.5 days).Ticket Ids:
    • SR-00309
    • TW//2020/S07808
    • TW/COTCORP/2020/S07818
    • TW/GEN/E107/2019
    • TW/eproc/2020/S07826
    • TW/BIHAREPROC/2020/S07825
    • Depts added on mails: GHBGOA

Chart Action Card

  • Homepage tickets and other tasks(1 day).Ticket Ids:
    • TW/CWC/2020/S07829
    • TW/INDBANK/2020/S07822
    • SR-00318
    • TW/ITISP/2020/S07832
    • LPPP Changes

Prev Next Chart

  • KT with homepage tickets

Expandable Chart

  • KT
  • Homepage tickets
    • TW/ITISP/2020/S07873
    • TW/LDA/2020/S07877
    • TW/eproc/2020/S07872
    • TW/COTCORP/2020/S07866
    • TW/DUSIB/2020/S07879
    • TW/DAMB/2020/S07880
    • TW/DSIIDC AUCTION/2020/S07886
    • TW/CEWACOR/2020/S07885
    • TW/CPWD/2020/S07887
    • TW/UPL/2020/S07892
    • SR-00314
    • SR-00315
    • TW/HPPCL/2021/S07903
    • TW/ITISP/2020/S07899
    • TW/RFCL/2020/S07895
    • TW/DAMB/2020/S07880
    • TW/DUSIB/2020/S07879
    • TW/GEN/2021/S07909